Wellington Fiber Project

Published 04/13/23

Wellington is where our roots were planted which made it an easy decision to begin building our fiber network in Wellington. In 2018 we began developing our fiber optics coverage throughout Wellington. We are currently offering fiber for a large portion of Wellington and are growing our service areas more every day. If you live in Wellington and are interested in our fiber services please view our Wellington Fiber Map below. If your street is featured on the map then contact us to learn more about our fiber services.

Current Streets That We Have Fiber Available:

Adams St, Barker St, Bennett St, Carpenter St, Clay St, Cornerstone Ave, Courtland St, Dewolf St, Dickson St, East St, Elm St, Erie St, Fieldstone Ct, Forest St, Grand Ave, Greenfield Ln, Greenview Ct, Grove St, Hale St, Hamilton St, E. Hamilton St, E Herrick Ave, W Herrick Ave, High St, Johns St, Jones Rd, Jones St, Kent St, Lincoln St, Magyar St, N. Main St, S. Main St, Meadow Ln, Mckinley St, Middle St, N. Mill St, S. Mill St, Montrose Way, Orchard Ln, Park Place, Parkside St, Pleasant St, Prospect St, Rabbit Run Ln, Sheila Dr, South St, Taylor St, Thornwood Dr, Union St, Vine St, Walden Ln, Waterford Way, Wenner St, West St, Wheeling St, Woodland St, & 4th St

Current Streets That We Are Building Fiber On But Is Not Available Yet:

Greenview Ct, Kelly St, N Main St

  • Progress to complete the fiber build in Wellington is over 80% of Wellington’s residences and continues in several neighborhoods. The underground fiber team has been busy boring conduit on the remainder of Sheila Drive and is currently heading towards Greenview Court. They hope to finish the underground work to pull strand and fiber through those areas and get them lit soon. When they are ready, we will be leaving door hangers at each address to ensure that residents know to call and schedule their installations.

    Meanwhile, the aerial team is working on completing Jones Road (Route 58 to Parkside). Aerial crews have finished building North Main Street (SR 58) from the railroad tracks north to Peck-Wadsworth Road, but are awaiting permission from CSX to get across tracks in order to light it up. Again, when each area is live, we will visit each address to ensure that residents know to call and schedule their installations.

  • Progress to complete the fiber build in Wellington continues in several neighborhoods. The underground fiber team has been busy boring conduit on Cornerstone Avenue, Waterford Way, North Mill Street, and is currently working on the north end of Wenner Street and Thornwood Drive. We hope to finish pulling strand and fiber through those areas and get them lit soon. When they are ready, we will be leaving door hangers at each address to ensure that residents know to call and schedule their installations.

    Meanwhile, the aerial team completed Jones Road (reservoir to Parkside), the east side of Parkside Street (Jones Road to high tensile wires), and a portion of Grand Avenue which is live and several customers have been installed. Aerial crews are currently working on building North Main Street (SR 58) from the railroad tracks north to Peck-Wadsworth Road, Montrose Way, and Kelly Street. They will follow with Clay Street, Hamilton Street (west side), south side of Sheila Drive, west end of Jones Street, and North Mill Street. Again, when each area is live, we will visit each address to ensure that residents know to call and schedule their installations.

  • Our Wellington Fiber Project progress has continued. We have lit-up service on the north side of Shelia Drive, so please feel free to call about our services if you are on the north side. We are also now able to offer our fiber services on Jones Road between the reservoir and Parkside Reserve; as well as, the east side of Parkside Street from Jones Road to the open farm field. We are currently boring on Cornerstone Ave so that we may provide fiber to the street. We do not have a current time frame for when this street will be active.

  • We have completed work on High Street, Vine Street, and Elm Street. Residents may call to schedule fiber installations or upgrades, NOW!

  • Crews are currently finishing the installation on SR 58 between Kent Street and Dollar General, the east side of Parkside, and Jones Road to the Metroparks site. Once that is complete, fiber crews will begin to work on Elm Street, High Street, and Vine Street.

  • We have completed Grand Avenue, McKinley Street, Wenner Street, and West Street. Residents may call to schedule fiber installations or upgrades, NOW! We will continue to build East Street and Jones Road over the next week.

  • Crews are 99% finished pulling strand on Grand Avenue (north of Dickson), McKinley Street, Wenner Street, and West Street. We will be cutting in taps this week and will begin fiber installations on these streets within the next two weeks. By the end of this week, residents on these streets can give us a call to set up installation appointments for new fiber service or conversion to fiber for existing customers. There is no charge to convert existing customers from wireless to fiber.